Orange Line work 60% complete, with help from $36.9 million in outside contracts
The MBTA has completed nearly 60% of planned work during the Orange Line shutdown, removed two of the six speed restrictions and is on track to resume service by Sept. 19. The update came Tuesday at Community College station, one … Continued